Loading Steel into Containers Without Wasting Freight

Nov 12, 2026

Leave a message

Lissandra
Lissandra
Export sales at Kennen Steel International. Works with overseas buyers on steel plate, coil and pipe sourcing from vetted Chinese mills.

Steel pipes strapped inside a shipping container

Steel is heavy, and containers are limited by weight long before they are limited by volume. Getting this wrong either leaves empty space you paid for, or produces an overweight container that cannot leave the port. Both cost money.

The weight ceilings you are working with

ContainerInternal volumeMax grossTypical payload (road-legal)
20GP~33 m³30.5 t25–27 t
40GP~67 m³30.5 t26 t
40HQ~76 m³30.5 t26 t
20OT / 40OTopen top, crane loaded30.5 tsame

The gross weight on the box is one limit. The other is the road limit at destination, which is often lower - many countries cap trucks at 24–26 t of cargo, and some ports and inland corridors are stricter. A container that is legal at the port can still be undeliverable at the customer's gate.

How steel actually loads

  • Coils - loaded on the roll, eye to sky, in cradles or wedged, single row for heavy coils. A 25 t coil cargo needs the floor spread, not concentration in one spot.
  • Plate and sheet - stacked flat, edge protectors, straps every 1.5 m, timber dunnage between bundles. Heavy plate goes on the floor, lighter bundles on top.
  • Pipe - nested and strapped, with timber between layers; beveled ends protected. Random lengths waste space, so cut-to-length pays for itself.
  • Sections (H-beams, channels) - nested to reduce voids, lashed to the floor rings, dunnage at contact points to prevent rubbing.
  • Fasteners and small items - palletised and shrink-wrapped; these are the volume-limited cargo, so they ride with the heavy goods.

Practical rules that save money

  1. Calculate the load before quoting freight. For plate: tonnes = m³ × 7.85. A 40HQ at 26 t holds about 3.3 m³ of solid steel - the rest is air and dunnage. Knowing that stops you quoting a "full container" that is 40% empty.
  2. Cut to length. Random 12 m pipe in a 40HQ wastes 5.8 m per container; two cut lengths of 5.8 m use it all.
  3. Respect the destination road limit, not just the box. Ask the buyer what the truck can legally carry from the port. We have seen 27 t containers held at the gate for a 24 t road limit.
  4. Photograph the loading. Photos of the stow, dunnage and seals are the cheapest insurance you have against a damage claim.
  5. Lashing, not hope. Steel moves. Straps to the floor rings every 1.5 m, timber blocking at the door end, and no reliance on friction.

What we do

  • Loading plan with the quotation when the order is container-based, showing tonnes, pieces and volume
  • Weight calculated against both the container limit and the buyer's road limit
  • Cut-to-length and nesting to reduce voids, quoted with the space it saves
  • Third-party pre-shipment inspection with a loading report and photos
  • Documentation checked so that the weights on the packing list, the bill of lading and the certificate agree

Tell us the destination port, the inland delivery point and the product mix. We will come back with a loading plan and a freight comparison, including whether a 20GP plus a 40HQ beats two 40HQs for your mix.

Related products: Hot rolled products, Steel pipes, Fasteners

Frequently asked questions

How many tonnes fit in a 40HQ container?

About 26 tonnes of payload, and often less once the destination road limit is applied.

What is the most expensive loading mistake?

Ignoring the inland truck limit. A container that is legal at the port can be undeliverable at the customer's gate.

How should steel coils be loaded?

On the roll, chocked or cradled, single row for heavy coils, with timber dunnage and straps every 1.5 m.