Dimensional Checks on Arrival: A Ten Minute Inspection That Pays for Itself
Claims fail for one reason: nothing was measured when the material arrived. A dimensional check on arrival takes about ten minutes per bundle, needs three tools, and is the difference between a replacement and an argument.
What you need
- A calibrated tape or steel rule, 5 m
- A micrometer or caliper for thickness
- A straight edge, 1 m, for flatness and bow
- A camera, with the date visible
Plate
- Thickness - measure at five points: four corners about 100 mm in from each edge, plus the centre. Record all five. The centre is where negative deviation usually shows.
- Width and length - measure at both ends. A length discrepancy of more than 10 mm on a 6 m plate signals a shearing problem.
- Flatness - lay the straight edge across the plate in both directions. Gaps over 8 mm per metre are outside normal mill tolerance for most grades.
- Edges - check for shear burrs and laminations visible at the edge.
Pipe and tube
- Outside diameter - measure at both ends, two directions each, to catch ovality
- Wall thickness - at both ends, four points each; eccentric wall is the most common defect
- Length - end to end, and check for square-cut ends
- Straightness - 0.2% of length is a common limit
Sections
- Depth and flange width - at both ends
- Web and flange thickness - at three points along the length
- Straightness and twist - a twisted beam will not fit the connection detail, and it will not show until erection
How to record it
Photograph the tape against the measurement, not a bare photo of the plate. Write the values into a simple sheet with the heat number, and send it to the supplier within the agreed claim period - usually 30 days from arrival, sometimes 15.
A claim without measurements is a complaint. A claim with five thickness readings, a photo and the heat number is a settlement.
What we do on our side
- Thickness measured at mid-point with a calibrated gauge before dispatch, values recorded
- Wall thickness of pipe checked at both ends and reported
- Dimensions and heat numbers on the packing list, so the arrival check can be matched line by line
- Third-party inspection available at the mill or at the port, with the report issued before shipment
Ask us for the pre-shipment measurement sheet with the documents. It costs nothing and it makes the arrival inspection a confirmation instead of an investigation.
Related: Plate weight tolerance, Hot rolled products, Steel pipes
Frequently asked questions
Where should I measure plate thickness?
At four corners about 100 mm in from the edges, plus the centre, which is where negative deviation usually shows.
What flatness tolerance is normal?
Gaps over 8 mm per metre are outside normal mill tolerance for most plate grades.
How long do I have to raise a claim?
Usually 15 to 30 days from arrival, depending on the contract. Measurements and photos decide the outcome.